Completion of construction under the guarantee case

KHC completes the construction of shared housing projects under the guarantee if the developer is unable to put the building into operation on time.

  • Shareholders receive 100% protection of their investments
  • The housing price remains unchanged
  • KHC ensures that the building is constructed in full compliance with all technical specifications

Reports on the progress of construction completion for all projects that received a guarantee from KHC

"Aliya" Residential Complex, Aktobe

Current Status:

The transfer and acceptance act for the participation share under trust management by JSC “KHC” has been signed.

Project Information:

The guarantee event was declared on 27 April 2026.

The total number of apartments is 280.

KHC contact regarding construction completion:

+7 7172 79 75 75 (ext. 3257)

8 800 080 44 48 — toll-free number


Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/332/

“Sparkle Diamond” Residential Complex, Ust-Kamenogorsk

Current Status:

The conclusion of the non-departmental comprehensive examination of projects has been received

Project Information:

Warranty case declared: August 29, 2024

Construction completion date:

November 2026.

Number of apartments: 93

KHC contact regarding construction completion:

+7 7172 79 75 75 (ext. 3258)

8 800 080 44 48 — toll-free number


Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/335/

“Asyl Tas” Residential Complex, Shymkent

Current Status:

The conclusion of the non-departmental comprehensive examination of projects was received. A joint activity agreement and a general contract agreement with Composite-7 LLP were concluded. Construction and installation work at the facility has been resumed. The planned completion date is June 2026.

Project Information:

Warranty case declared: September 25, 2024

Construction completion date:

June 2026.

Number of apartments: 103

KHC contact regarding construction completion:

+7 7172 79 75 75 (ext. 3257)

8 800 080 44 48 — toll-free number


Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/275/

“JM City” Residential Complex, Astana

Current Status:

Construction and installation works are in progress

Project Information:

Warranty case declared: October 21, 2024

Construction completion date:

I Phase - August2026;

II Phase - August 2026.


Number of apartments: 390

KHC contact regarding construction completion:

+7 7172 79 75 75 (ext. 3256)

8 800 080 44 48 — toll-free number


Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/133/

 

 

 ​