Completion of construction under the guarantee case

KHC completes the construction of shared housing projects under the guarantee if the developer is unable to put the building into operation on time.

  • Shareholders receive 100% protection of their investments
  • The housing price remains unchanged
  • KHC ensures that the building is constructed in full compliance with all technical specifications

Reports on the progress of construction completion for all projects that received a guarantee from KHC

Residential Complex “Sparkle Diamond”, Ust-Kamenogorsk

Current Status:

The conclusion of the non-departmental comprehensive examination of projects was received. A joint activity agreement and a general contract agreement with «Composite-7» LLP were concluded. Construction and installation work at the facility has been resumed. The planned completion date is November 2026.

Project Information:

Warranty case declared: August 29, 2024

Construction completion date:

November 2026.

Number of apartments: 93

KHC contact regarding construction completion:

+7 7172 79 75 (ext. 2733)

Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/335/

Residential Complex “Asyl Tas”, Shymkent

Current Status:

The conclusion of the non-departmental comprehensive examination of projects was received. A joint activity agreement and a general contract agreement with Composite-7 LLP were concluded. Construction and installation work at the facility has been resumed. The planned completion date is June 2026.

Project Information:

Warranty case declared: September 25, 2024

Construction completion date:

June 2026.

Number of apartments: 103

KHC contact regarding construction completion:

+7 7172 79 75 (ext. 2728)

Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/275/

Residential Complex “JM City”, Astana

Current Status:

Construction and installation works are in progress

Project Information:

Warranty case declared: October 21, 2024

Construction completion date:

I Phase - April 2026;

II Phase - August 2026.


Number of apartments: 390

KHC contact regarding construction completion:

+7 7172 79 75 (ext. 2726)

Link to Engineering Company Report:

https://khc.kz/ru/engineering-otchet/133/

 

 

 ​